- Categories: Cooling, Portable Air Conditioners
- Industries: Facility Management, Data Centres, Commercial
- Location: North Sydney, NSW
- Client: Telstra
The Problem
Telstra faced an urgent need for a cooling solution in their server room following a sudden air conditioning malfunction. Without proper temperature control, critical server equipment was at risk of overheating, potentially causing significant downtime and operational disruptions.
The Challenge
The client required an immediate and reliable cooling solution to stabilise the server room’s temperature. The system needed to be deployed quickly, operate efficiently in a high-heat environment, and ensure uninterrupted cooling to protect sensitive equipment.
The Solution
We supplied and installed two 6kW portable air conditioners to address the server room’s cooling requirements. The units were strategically placed to optimise airflow and maintain a stable temperature throughout the space. Their robust performance and maintenance-free design provided Telstra with a reliable solution to eradicate the cooling issue and safeguard their IT infrastructure.